Citation : 2024 Latest Caselaw 14763 Kant
Judgement Date : 27 June, 2024
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 27TH DAY OF JUNE, 2024
BEFORE
THE HON'BLE MR. JUSTICE R.NATARAJ
WRIT PETITION NO.55953 OF 2016 (GM-FOR)
BETWEEN:
NSL RENEWABLE POWER PVT. LTD.,
REGD. OFFICE AT NSL ICON,
NO. 8-2-684/2/A, PLOT NO. 1 TO 4,
4TH FLOOR, ROAD NO. 12,
BANJARA HILLS,
HYDERABAD-500034.
REP. BY ITS SENIOR MANAGER (LIAISON),
SRI. M. VENKAT
...PETITIONER
(BY SRI. K.N.PHANINDRA, SENIOR ADVOCATE FOR
SMT. VAISHALI HEGDE, ADVOCATE)
AND:
1. STATE OF KARNATAKA,
REP. BY ITS SECRETARY,
DEPARTMENT OF FORESTS,
ECOLOGY AND ENVIRONMENT,
4TH FLOOR, M.S. BUILDING,
DR. AMBEDKAR ROAD,
BANGALORE-560 001.
2. THE PRINCIPAL CHIEF CONSERVATOR OF FORESTS,
"ARANYA BHAVAN",
18TH CROSS,
MALLESWARAM,
BANGALORE-560 003.
2
3. THE DEPUTY CONSERVATOR OF FORESTS
DAVANAGERE REGIONAL DIVISION,
DAVANAGERE-577 005.
...RESPONDENTS
(BY SRI. S.T. NAIK, ADDITIONAL GOVERNMENT ADVOCATE FOR
RESPONDENT NOS.1 TO 3)
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 OF
THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
DEMAND NOTICE DATED 19.09.2016 BEARING
NO.A2/LAND/KALLUGANI/CR-50/2008-09 VIDE ANNEXURE-A
AND THE REVISED DEMAND NOTICE DATED 19.09.2016
BEARING NO.A2/LAND/KALLUGANI/CR-50/2008-09 VIDE
ANNEXURE-A1 BOTH ISSUED BY THE 3rd RESPONDENT AND ALL
FURTHER PROCEEDINGS/ACTIONS THERETO.
THIS PETITION HAVING BEEN HEARD AND RESERVED
FOR ORDER ON 02.04.2024 AND COMING ON FOR
PRONOUNCEMENT OF ORDER THROUGH VIDEO CONFERENCE
THIS DAY, THE COURT MADE THE FOLLOWING:-
ORDER
The petitioner has challenged the demand notice
dated 19.09.2016 bearing No.A2/Land/Kallugani/CR-
50/2008-09 and the revised demand notice dated
19.09.2016 bearing No.A2/Land/Kallugani/CR-50/2008-09
calling upon it to pay a sum of Rs.1,82,01,430/- along with
interest at the rate of 12% per annum.
2. The petitioner had proposed to establish a wind
power project in Guheshwaragudda Reserve Forest in
Jagalur Taluk, Davanagere District and hence, sought for
prior approval under Section 2 of the Forest Conservation
Act, 1980 (henceforth referred to as 'Act, 1980') from the
Ministry of Environment, Forests and Climate Change,
Government of India (MOEF). After considering the
proposal, MOEF passed an order dated 17.03.2003
conveying its Final Approval (Stage - II) under Section 2
of the Act, 1980 for diversion of 19.94 hectares of land in
Guheshwaragudda Reserve Forest in favour of the
petitioner for establishment of 17.25 MW wind farm. The
State Government passed an order dated 12.05.2003
granting sanction for establishment of the wind farm. The
forest land was leased for a period of ten years.
Thereafter, MOEF issued guidelines dated 17/18.09.2003
regarding collection of Net Present Value (NPV) from user
agencies in view of the Orders dated 30.10.2002 and
01.08.2003 passed by the Hon'ble Supreme Court of India
in T.N. Godavarman case (W.P.(Civil) No.202/1995). It is
claimed that NPV was to be charged on all those cases
which were granted in-principle approval after 30.10.2002.
The rate of NPV ranged between Rs.5.80 lakhs per hectare
to Rs.9.20 lakhs per hectare. The respondent No.3 issued
a notice dated 15.12.2004 demanding the petitioner to pay
a sum of Rs.1,19,68,800/- being the NPV for 19.940
hectares of forest land leased in favour of the petitioner.
The petitioner paid the said sum under protest by a
banker's cheque. The petitioner had informed that it had
filed an application before the Hon'ble Supreme Court
regarding the liability to pay NPV and that the application
was pending. It claimed that in order to avoid stoppage of
the project, it had paid the NPV 'Under Protest'. The
petitioner claimed that the Hon'ble Supreme Court passed
an order dated 24.04.2008 in W.P.(Civil).No.202/1995 on
the applications filed by it as well as other applicants and
directed that the applicants who were permitted to
establish wind energy project should pay 50% of NPV at
the minimum rate charged, provided minimum tree felling
was involved. The MOEF thereafter addressed a letter
dated 29.12.2008 to all State Governments about the
Order dated 24.04.2008 passed by the Hon'ble Supreme
Court that NPV is payable at 50% of the minimum rate
irrespective of the eco-class in which the project lay.
Following this, the MOEF issued another set of guidelines
dated 05.02.2009 post the judgment of the Hon'ble
Supreme Court dated 28.03.2008 by which, the rates of
NPV was re-fixed on the basis of scientific data taking into
account the economical role and value of forests. In this
guidelines, the lowest rate of NPV specified therein was
Rs.4,38,000/- per hectare. It was clarified in this guideline
that NPV in respect of wind energy projects was to be
levied at 50% of minimum rate of NPV irrespective of the
eco-class, in which the project lay.
3. The petitioner contends that it had
commissioned the project in the land leased to it but had
utilized 17.577 hectares of forest land out of 19.94
hectares, which was granted. In addition, the petitioner
had utilized 19.42 hectares of land for establishment of the
project. The period of lease of 19.94 hectares expired on
11.05.2013. The petitioner contends that though it sought
refund of the excess amount of NPV paid, the same was
not considered. Thereafter, the petitioner sought renewal
of the forest clearance in respect of 17.577 hectares and
19.42 hectares of additional land that was utilized.
4. The petitioner contends that the Hon'ble
Supreme Court passed another Order dated 02.12.2013 in
W.P.(Civil).No.202/1995 and specifically clarified that the
applicant therein should be given the benefit of claiming
only 50% NPV even though the project may have started
prior to the Order dated 24.03.2008 by which, the
aforesaid exemption of 50% NPV was granted.
Subsequently, MOEF passed an Order dated 26.05.2015
conveying its in-principle Stage-I approval for renewal of
37 hectares (17.577 + 19.42 hectares) of forest land at
Guheshwaragudda in favour of the petitioner. Two
conditions were imposed in the approval, which were as
follows:
"Condition No.5 : The user agency shall pay NPV at full rate. The State Government shall also realize interest at 12% per annum
compounded annually on the Net Present Value amount from the date the amount became due till date of realizing of the same from the user agency.
Condition No.6 : The user agency shall pay a penalty of not less than two times of NPV for the excess forest land utilized by the user agency in violation of Forest Conservation Act, 1980 in addition to the levy of regular Net Present Value."
5. The MOEF addressed a letter dated 22.07.2015
clarifying that NPV at full rate is to be levied on the user
agency as per condition Nos.5 and 6, referred above,
which meant 100% of the minimum rate of NPV
irrespective of the eco-class in which, the project lay
instead of 50% of NPV at the minimum rate charged. The
respondent No.2 thus addressed a letter dated 11.08.2015
to the respondent No.3, with a copy marked to the
petitioner and directed the respondent No.3 to take
necessary action for realization of NPV at full rate from the
petitioner along with interest at 12% per annum.
Subsequent thereto, the respondent No.1 addressed a
letter dated 27.08.2015 to the Principal Chief Conservator
of Forest (PCCF), Bengaluru, intimating that the petitioner
company had paid a sum of Rs.1,19,68,800/- instead of
Rs.43,66,860/- being 50% of NPV at the rate of
Rs.4,38,000/- per hectare and therefore, excess of
Rs.76,01,940/- was paid. The State Government directed
the PCCF, Bengaluru, to adjust or give credit of
Rs.76,01,940/- and collect the balance amount as per the
condition No.5 imposed by MOEF in its order dated
26.05.2015. Later, the respondent No.3 issued a demand
notice dated 08.01.2016 calling upon the petitioner to pay
a sum of Rs.5,29,96,652/- as per condition Nos.5 and 6
referred above. The respondent No.3 had calculated the
full amount of NPV instead of 50% at the rate of
Rs.4,38,000/- per hectare for an extent of 19.42 hectares
of additional land utilized land along with penalty at the
rate of two times of NPV at Rs.4,38,000/- per hectare and
gave credit of Rs.76,01,940/- that was paid earlier. The
petitioner sought time to make the said payment and
accordingly the time was extended upto 26.05.2016.
Thereafter, the petitioner paid the entire amount as
demanded. The petitioner contends that when such being
the facts, the Accountant General had raised an audit
objection regarding the manner in which the respondent
No.3 had calculated and levied the NPV on the petitioner at
the rate of Rs.4,38,000/- per hectare instead of
Rs.5,80,000/- per hectare, thus resulting in a short levy of
Rs.2,22,00,000/-. A letter in that regard was addressed to
the respondent No.2 on 19.07.2016. The respondent No.3
therefore, summoned the officers of the petitioner on
08.08.2016 and orally asked the petitioner to pay up the
amount and directed not to operate the nine Wind Turbine
Generators. The petitioner claims that under compelling
circumstances, it furnished an undertaking dated
08.08.2016 to pay the amounts as claimed in the audit
objections. Thereafter, the respondent No.2 addressed a
letter dated 30.08.2016 to the respondent No.1 and had
marked a copy to the petitioner, wherein it was narrated
about the grant of forest land to the petitioner and audit
objections regarding short levy of Rs.2.2 crores. The
respondent No.2 referred to the letter dated 09.08.2016 of
the Deputy Conservator of Forest, wherein he had stated
that the action taken by his office with regard to complying
the stipulated conditions in Stage - I approval of MOEF
was as per law and that the audit observation be dropped.
Thus, the respondent No.2 had requested the respondent
No.1 to apprise the Accountant General of the facts of the
case and to obtain necessary directions. The petitioner
contends that to its shock and surprise, the respondent
No.3 issued a demand notice dated 19.09.2016 and
revised demand notice dated 19.09.2016 calling upon the
petitioner to pay a sum of Rs.1,82,01,430/- along with
interest at 12% per annum upto the date of payment. The
petitioner contends that this demand was in the light of
the audit objections and audit note raised by the
Accountant General, Karnataka. Thereafter, the
respondent No.3 informed the petitioner by letter dated
24.09.2016 that permission has been granted to start nine
Wind Turbine Generators that were stopped, subject to
payment of all dues on or before 24.10.2016. The
petitioner therefore, submitted a detailed representation
dated 17.10.2016 denying its liability to pay the amount as
demanded and specifically informed the respondents that
NPV had to be charged at the rate of Rs.4,38,000/- per
hectare, which was the minimum rate.
6. The petitioner being aggrieved by the said
demand dated 19.09.2016 and revised demand dated
19.09.2016 has filed this writ petition.
7. The learned Senior counsel for the petitioner
submitted that as per the Guidelines dated 05.02.2009
issued by the MOEF, in respect of wind energy project 50%
of the minimum rate of NPV irrespective of the eco-class in
which the project lay had to be collected. He submitted
that the minimum NPV was a sum of Rs.4,38,000/- per
hectare and therefore, even as per condition Nos.5 and 6
referred above, the petitioner was liable to pay NPV of
Rs.4,38,000/- per hectare on 19.42 hectares of land and
penalty of two times of NPV for the excess forest land
utilized. He therefore, contended that the audit objection
that the petitioner was liable to pay NPV at the rate of
Rs.5.80 lakhs per hectare is incorrect. He also referred to
the Order passed by the Hon'ble Supreme Court dated
02.12.2013 on I.A.Nos.2785, 3025 and 3390 in W.P.(Civil)
No.202/1995, where it was held,
"Considering the fact that Central Empowered Committee had recommended that wind energy projects be given extra 50 percent of the Net Present Value at the minimum rate for the reason that wind energy projects were eco- friendly, we are the opinion that the project of the applicant should be given the said benefit of paying only 50 percent Net Present Value even though the project may have started prior to the order dated 24th March, 2008."
8. Learned Senior counsel therefore, contends
that even if condition Nos.5 and 6 of the in-principle
approval dated 26.05.2015 is taken into account, the NPV
had to be calculated at 100% of the minimum rate and not
at Rs.5,80,000/- per hectare. He contends that the
petitioner has already paid up a sum of Rs.5,29,96,000/-
on 26.07.2016 and therefore, the impugned demand was
incorrect.
9. The petition is opposed by the respondents
who have filed a detailed statement of objections. The
respondents contend that the Hon'ble Supreme Court vide
its order dated 30.10.2002, had directed all States and
Union Territories to collect the NPV for the forest land
approved for non-forestry purposes between Rs.5.80 lakhs
and Rs.9.20 lakhs per hectare. It is contended that the
Government of India, Ministry of Environment and Forest,
New Delhi, vide its letter dated 11.08.2003 had directed
the state Governments to comply the order of the Hon'ble
Supreme Court dated 30.10.2002. The State Government
vide its letter dated 17.01.2004 had thus issued order of
collection of NPV in compliance with the aforesaid order.
The respondents admitted that the petitioner sought
permission to establish a wind power project at
Guheshwaragudda Reserve Forest and permission was
granted by the MOEF vide letters dated 12.12.2002,
17.03.2003 and 05.08.2004. It is contended that the
petitioner was directed to pay NPV of Rs.1,19,68,800/- for
diversion of 19.94 hectares of forest land and the
petitioner deposited the said amount. It is contended that
the petitioner had encroached into and utilized 19.42
hectares of additional forest land, which came to the notice
of the MOEF during an inspection. Thereafter, an FIR was
lodged but was not proceeded with as the proposal for
renewal of 37 hectares was submitted to the MOEF. The
MOEF taking into consideration the earlier lease, extended
the project period for a further period of 20 years which
was subject to compliance of 17 conditions. The petitioner
made a representation to the MOEF on 07.07.2015 to
modify the condition relating to payment of NPV as per the
order dated 28.03.2008. A clarification was issued by
MOEF vide letter dated 29.12.2008 that NPV at full rate
should be levied on the petitioner and that the petitioner
was not entitled to the benefit of the order of the Hon'ble
Supreme Court dated 28.03.2008. It contended that the
respondent No.2 erroneously directed the respondent No.3
to take necessary action for realization of NPV at full rate
and interest at 12% per annum compounded annually by
the user agencies as the minimum rate of NPV was
Rs.4,38,000/- per hectare as per the order of the Hon'ble
Supreme Court dated 28.03.2008. It is contended that the
Hon'ble Supreme Court vide its order 28.03.2008 had
specifically stated in para (iii) that,
"these NPV rates may be made applicable with prospective effect except in specific cases such as Lower Subhanshri Project, mining leases of SECL, field firing ranges, wherein pursuant to the orders passed by this Hon'ble Court, the approvals have been accorded on lumpsum payment/no payment towards NPV."
10. The respondent No.3 thereafter issued a
demand notice dated 08.01.2016 demanding NPV in
respect of renewal of 37 hectares of land being utilized by
the petitioner and that the same was paid. It is contended
that during the audit scrutiny, the mistakes and lapses
committed by the respondents was noticed and hence,
Principal Accountant General, Bengaluru, by its letter dated
19.07.2016 addressed to the Additional Chief Secretary,
Department of Forest, sought explanation for short levy of
NPV and penal charges amounting to Rs.2.22 crores. On
receiving the said communication, the respondents
initiated action to recover the pending dues from the
petitioner by raising a demand dated 19.09.2016 and the
revised demand dated 19.09.2016.
11. It is contended that the petitioner had
encroached into the forest land and suppressed this fact
when it filed an application in W.P.(Civil) No.202/1995.
Therefore, it was denied the benefit of the orders of the
Hon'ble Supreme Court in respect of calculating the NPV
for the Windmill project by the MOEF vide letter dated
22.07.2015. It is contended that the Principal Accountant
General had rightly held that minimum rate of NPV
applicable to the petitioner was Rs.5.80 lakhs per hectare.
It is also contended that the Hon'ble Supreme Court had
specifically stated in its order dated 28.03.2008 that the
revised NPV is applicable prospectively. It is contended
that since the petitioner had undertaken to pay the
balance amount, it is bound to pay the same.
12. It is further contended that the petitioner had
encroached and utilized excess area of 19.42 hectares and
had installed nine additional towers outside the lease area
with effect from March, 2004 itself and therefore, the
petitioner was liable to pay NPV at Rs.5.80 lakhs per
hectare as per the rates fixed by the Government of
Karnataka by its notification dated 17.01.2004, which was
in force. Therefore, it is contended that the petitioner
cannot take advantage of the order passed by the Hon'ble
Supreme Court revising the rates of NPV and therefore,
contended that the petitioner is not entitled to any reliefs
in this petition.
13. I have considered the submissions of the
learned Senior Counsel for the petitioner as well as the
learned Government Advocate. I have also perused the
documents enclosed with the writ petition as well as the
statement of objections.
14. The Hon'ble Apex Court, while considering
I.A. Nos.1224 and 1225 filed by applicants who were
engaged in generating electricity from wind turbines in
T.N. Godavarman Thirumulpad vs. Union of India and
Others, accepted the suggestion of the Central
Empowered Committee to grant 50% exemption from
payment of NPV and passed an order dated 24.04.2008
and held that Wind Energy Project proponents shall be
granted exemption of 50% of the NPV provided, there is
minimal tree felling. Following this, the Government of
India in terms of its letter dated 29.12.2008 clarified that
in respect of wind energy projects, the NPV is payable at
50% of the minimum rate of the NPV, irrespective of the
eco-class in which the project was established. As per the
chart prescribed in the guidelines dated 05.02.2009 issued
by the Government of India, the minimum NPV was a sum
of Rs.4,38,000/- per hectare. As rightly contended by the
learned Senior Counsel for the petitioner, the benefit of
this reduced 50% of minimum NPV was given to all wind
energy projects established prior to 24.03.2008 by the
Hon'ble Apex Court while considering I.A. Nos.2785, 3025
and 3390 in T.N. Godavarman Thirumulpad's case
referred supra. Later, the Government of India
presumably, having been informed that the petitioner had
encroached into additional 19.42 hectares of forest land,
granted in-principle approval (Stage-I) for renewal of 37
hectares of forest land by the petitioner for the wind farm
project in terms of the communication dated 26.05.2015,
but mistakenly imposed a condition that the petitioner
should pay the NPV at full rate. Soon thereafter, the Chief
Conservator of Forests (Central) addressed a letter dated
22.07.2015 to the Additional Chief Secretary to
Government of Karnataka, Forest, Ecology and
Environment Department clarifying that, the condition to
pay NPV at full rate meant 100% of the minimum rate of
NPV charged as per the earlier letter dated 29.12.2008.
This therefore meant that NPV had to be paid at
Rs.4,38,000/- per hectare. Consequent thereto, the
petitioner has paid up the 100% of the NPV amounting to
Rs.5,29,96,652/- as demanded by respondent No.3 vide
his letter dated 08.01.2016. It now appears that the
Principal Accountant General (E&RSA), Karnataka,
Bangalore have raised an audit objection on 19.07.2016
that a sum of Rs.2,22,00,000/- was short levied on the
petitioner by not complying with condition No.5 in the
in-principle approval dated 26.05.2015 that NPV at full
rate was payable. Consequent to this, the respondents
have issued a notice of demand dated 19.09.2016
demanding the sum of Rs.1,82,01,430/- by factoring NPV
at Rs.5,80,000/- per hectare. This apparently was without
reference to the clarification dated 22.07.2015 referred
above, which clarified that condition No.5 mentioned in the
in-principle approval meant 100% of the minimum NPV
which was Rs.4,38,000/- per hectare. This clarification was
also in line with the guidelines prescribed by the
Government of India on 29.12.2008. Therefore, the
demand of NPV by the respondents at Rs.5,80,000/- per
hectare is wholly incorrect and deserves to be interfered
with. Hence, the following:
ORDER
i. The writ petition is allowed.
ii. The impugned Demand Notice dated
19.09.2016 bearing No.A2/ Land/ Kallugani/
CR-50/2008-09 and the Revised Demand
Notice dated 19.09.2006 bearing No.A2/ Land/
Kallugani/CR-50/2008-09 issued by respondent
No.3 are quashed.
iii. The respondent No.3 is directed to adjust the
amounts already paid by the petitioner towards
NPV at 100% of Rs.4,38,000/- per hectare
along with interest, if any payable and refund
any excess amount to the petitioner. This shall
be complied within a period of two months
from the date of receipt of a copy of this order.
iv. Before parting from the case, the petitioner,
who was granted permission to divert 19.94
hectares for Non-Forestry purpose, had
encroached into an additional 19.42 hectares.
It is not known whether the petitioner has
raised compensatory Afforestation over an
equivalent area of identified non-forest land at
its cost. Therefore, respondent No.3 shall
ascertain this and ensure compliance.
v. In view of disposal of the main petition,
I.A.1/2021 for vacating interim order does not
survive for consideration and is accordingly
dismissed.
Sd/-
JUDGE PMR/LG
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!